Hampton, Rose Bay consists of 22 high
end residential apartments above a 2 level
basement. With a tight mobilisation period,
Lords Group quickly mobilised the design
team to finalise CC documentation and
was able to commence on site within 7
weeks of engagement.
Project challenges included construction
frontages to Old South Head Rd being
an RMS asset with strict limitations, 460
9.5m contiguous piles including temporary
steel whalers and anchors to shore the 2
levels of sand ground conditions, as well
as boundary to boundary construction
with protection of councils footpaths and
egress to be maintained throughout the
construction period.